Road ConditionsFeaturedInyo CountyNews
Whitney Portal Construction Update for the Weeks of July 27, 2024 to August 22, 2024
CONSTRUCTION UPDATE FOR THE WEEKS OF July 27, 2024 to August 22, 2024
Project Number: CA ER INYO 2023-4(1)
Project Name: Whitney Portal Road
Contractor: Steelhead Constructors JV PO
Award Date: July 03, 2024
Notice to Proceed Date: July 10, 2024
Contract Completion Date: December 31, 2024
Award Amount: $4,599,230.00
Estimated % Time: 25 % (44 days of 175 days)
Estimated % Work: 35 %
Description of Work: Road reconstruction and armoring, guardrail improvements, drainage improvements, slope scaling
Report Prepared by: Barbara Quintana
Work in Progress:
Embankment:
- Foundation grade prep work complete
- Construction of embankment ongoing
- Borrow haul began the week of August 20th and will continue thru the week of August 26th
- Embankment work approximately 45 % complete
Riprap:
- Embankment Protection Station 655+50 Lt to Station 658+50 Lt complete
Removals of Structures and Obstructions:
- Removal of existing asphalt complete
- Existing pipe at Station 668+64 has been removed and backfilled.
Traffic Control:
- Message Boards and Signs in place along designated detour route. SB Message Board on US 395 was repaired by end of shift on 08/22/24.
Work Schedule:
- Monday thru Friday and Saturdays as needed Shift hours 0600 – 1600
- Labor Day Weekend: No work 08/30/24 thru 09/03/24








Discover more from Eastern Sierra Now | Local News
Subscribe to get the latest posts sent to your email.









