Road ConditionsFeaturedInyo CountyNews

Whitney Portal Construction Update for the Weeks of July 27, 2024 to August 22, 2024

CONSTRUCTION UPDATE FOR THE WEEKS OF July 27, 2024 to August 22, 2024 

Project Number: CA ER INYO 2023-4(1)

Project Name: Whitney Portal Road

Contractor: Steelhead Constructors JV PO

Award Date: July 03, 2024

Notice to Proceed Date: July 10, 2024

Contract Completion Date: December 31, 2024

Award Amount:  $4,599,230.00

Estimated % Time: 25 % (44 days of 175 days)

Estimated % Work: 35 %

Description of Work: Road reconstruction and armoring, guardrail improvements, drainage improvements, slope scaling

Report Prepared by: Barbara Quintana

Work in Progress: 

Embankment: 

  • Foundation grade prep work complete
  • Construction of embankment ongoing
  • Borrow haul began the week of August 20th and will continue thru the week of August 26th
  • Embankment work approximately 45 % complete

Riprap: 

  • Embankment Protection Station 655+50 Lt to Station 658+50 Lt complete

Removals of Structures and Obstructions:  

  • Removal of existing asphalt complete
  • Existing pipe at Station 668+64 has been removed and backfilled.

Traffic Control: 

  • Message Boards and Signs in place along designated detour route. SB Message Board on US 395 was repaired by end of shift on 08/22/24.

Work Schedule: 

  • Monday thru Friday and Saturdays as needed Shift hours 0600 – 1600
  • Labor Day Weekend: No work 08/30/24 thru 09/03/24

whitney portal

whitney portal

WHITNEY PORTAL ROAD CONSTRUCTION UPDATE 08.23.2024 3

WHITNEY PORTAL ROAD CONSTRUCTION UPDATE 08.23.2024 4

whitney portal

whitney portal

whitney portal


Discover more from Eastern Sierra Now | Local News

Subscribe to get the latest posts sent to your email.

Related Articles

Back to top button
Close

Adblock Detected

We make money by selling ads to out platform. Please show the advertisements so we can keep the website free to you. Support local news.